Open-book delivery where the owner keeps visibility and control of every trade contract.

Under a construction management contract (CCDC 5A), Westland acts as the owner's construction partner. We tender and manage trade contracts on the owner's behalf with full cost transparency, and bring pre-construction insight to design decisions before they are locked in.

Case studies

Construction Management in practice.

All projects
Pure
Pure 2
Pure 3

CCDC 5A Construction Management · Under construction

Pure

Cambie Corridor, Vancouver

A mixed-use community at 49th and Columbia on the Cambie Corridor, delivered open-book with every trade contract visible to the owner.

$53M

Construction value

101,180

Square feet

25

Executed trade contracts

  • Trade tendering, levelling and award recommendations for the owner
  • Monthly cost reports and quantity-surveyor certified draws
  • Owner-consultant coordination, schedule and closeout planning
View project
W19th

Pre-construction & Construction Management · Pre-construction

W19th

Dunbar, Vancouver

A four-storey residential building over ground-floor commercial on the Dunbar corridor.

$15.55M

Budget

28,842

Square feet

  • Constructability review and budgeting
  • Trade market sounding and procurement planning
  • Cost control carried into construction
View project

Our approach

How we deliver it, step by step.

  1. 01

    Contract briefing

    On execution, key dates, notice periods, payment terms, insurance and any unusual supplementary conditions are summarized and briefed to the whole project team.

  2. 02

    Cost-coded budget baseline

    The estimate is carried into job cost by cost code and reconciled to the schedule of values. Every later budget change is a recorded adjustment with a reason and an approval.

  3. 03

    Trade tendering for the owner

    Tender packages define scope, schedule, site conditions, safety and insurance. Bids are levelled like-for-like, and each award recommendation states price against budget, scope confirmations and risks.

  4. 04

    Monthly cost report and forecast

    Budget, committed, incurred, cost to complete and forecast final cost by cost code. Owner contingency is tracked on its own line and drawn only with owner authorization.

  5. 05

    Certified progress claims

    Trade claims are checked against work in place before certification. Claimed, quantity-surveyor certified and paid amounts are reconciled line by line, with statutory holdback administered throughout.

  6. 06

    Transparent change log

    Every potential change is logged within two business days, priced with backup and flowed down to trades. Contemplated, submitted and approved changes are reported together.

What you receive

Deliverables

  • →Monthly job cost report with forecast final cost and contingency status
  • →Bid levelling sheets and written award recommendation per trade package
  • →Change log of contemplated, submitted and approved changes
  • →Monthly draw package reconciled to quantity surveyor certification
  • →Bi-weekly owner meetings, weekly in critical phases, with minutes
  • →Holdback ledger by trade and statutory declarations at each payment

Standards we hold

Controls

  • CCDC 5A with the owner's supplementary conditions; the contract governs
  • BC Builders Lien Act 10% holdback, released only after the lien period and search
  • Written delegation-of-authority limits for awards, changes and contingency draws
  • Cost-code variances above threshold require a written explanation and action plan